Schedule

DateWork
March 1 - 6, 2017Relocation of existing infrastructure (playground equipment, bike lockup, light standards and vehicle charging station)
March 8, 2017Site construction fencing in place
mid-March, 2017Former public works building (blue building across from Public Safety Building on Park Place) demolished and removed
March 10 - 31, 2017Remediation of the ETS site
April, 2017Relocation of storm/sanitary services 
April, 2017Construction of ETS commences

This project schedule will be revised and updated as more information becomes available.