DateWork
March 1 - 6, 2017Relocation of existing infrastructure (playground equipment, bike lockup, light standards and vehicle charging station)
March 8, 2017Site construction fencing in place
mid-March, 2017Former public works building (blue building across from Public Safety Building on Park Place) demolished and removed
April, 2017Relocation of storm/sanitary services 
August, 2017 - April 2018Remediation activities
April 2018Aragon commences construction activities: foundation work and site preparation
June/July 2018Relocation of storm/sanitary services & site servicing

This project schedule will be revised and updated as more information becomes available. Please visit the Aragon website for additional project information and timeline.