| Date | Work |
| March 1 - 6, 2017 | Relocation of existing infrastructure (playground equipment, bike lockup, light standards and vehicle charging station) |
| March 8, 2017 | Site construction fencing in place |
| mid-March, 2017 | Former public works building (blue building across from Public Safety Building on Park Place) demolished and removed |
| April, 2017 | Relocation of storm/sanitary services |
| August, 2017 - April 2018 | Remediation activities |
| April 2018 | Aragon commences construction activities: foundation work and site preparation |
| June/July 2018 | Relocation of storm/sanitary services & site servicing |
This project schedule will be revised and updated as more information becomes available. Please visit the Aragon website for additional project information and timeline.