Equipment delay extends Esquimalt Recreation Centre pool closure

Type(s)
News

News release
FOR IMMEDIATE RELEASE

Esquimalt, BC­­—The Township of Esquimalt is extending the temporary closure of its aquatic facility due to delays in a key piece of new HVAC equipment.

The aquatic facility closed on November 22, 2026 for a planned three-week shutdown to accommodate annual maintenance activities and the replacement of aging HVAC infrastructure. The Township has since been advised that a key piece of replacement equipment has been delayed during manufacturing, affecting the project's completion schedule and reopening timeline. The fitness centre and other recreation services remain open and on their regular schedules.

While the exact duration of the delay is still being determined, the manufacturer has indicated a high degree of confidence that the equipment delay will prolong the opening of the pool from December 14 to December 23.

"We recognize this is disappointing news for our residents, aquatic user groups, program participants, and staff," said Steve Knoke, Director of Parks and Recreation Services. "We understand how important aquatic services are to our community and the impact that an extended closure will have on individuals and families who rely on the facility for recreation, fitness, lessons, and social connection."

The aquatic facility, including the pool, sauna and hot tub, is shut down annually for routine maintenance of key operating equipment, typically for three weeks. The shutdown this year was carefully coordinated to include additional needed roof repairs and importantly replacing an aged HVAC unit. The aim was to reduce overall facility downtime and staffing disruptions by scheduling the facility maintenance and capital improvement projects concurrently.  

The HVAC replacement project remains a critical investment in the long-term operation, reliability, and efficiency of the aquatic facility. While the delay is outside of the Township's control, staff and project partners are actively pursuing opportunities to minimize the impact on the project schedule and reduce the duration of the closure.

The extended closure will affect public swimming, aquatic fitness programs, user group rentals, and other aquatic programming. Staff are in communication with user groups and the Township is committed to providing regular updates and will announce a revised reopening date once greater certainty is established. In the meantime, Oak Bay Rec, Saanich, Westshore, SEAPARC, and Panorama pools are honouring Esquimalt passes.  

"We appreciate the patience, understanding, and support of our community as this important infrastructure project moves forward," added Knoke. "Our focus remains on completing the work safely and efficiently and restoring aquatic services as quickly as possible."

For updates, please visit www.esquimalt.ca and follow the Township of Esquimalt's social media channels.

-30-