January 2020

We are in the detailed design phase of the Gorge Park Pavilion project with local firm Iredale Architecture as the lead consultant and architect group. The design is based on previous public feedback and council direction. We anticipate the building being under construction this summer.

Fall 2019

Staff are developing some initial concept design plans for Gorge Park. This will facilitate further analysis and allow for the development of preliminary capital and operating budget estimates. This work is being undertaken this spring and findings should be reported to Council in early fall.

March 2019

Council reviewed the evaluated projects and further refined the list of project ideas.

January 2019

Council approved selection criteria for the evaluation and scoring of the multiple projects identified during the two rounds of public engagement and directed staff to apply the selection criteria to the projects. 

October-December 2018

Survey input compilation 

September 23, 2018

Deadline for input: Round 2 Survey

May 2018

Round 2 Online Survey opens and mobile engagement booth launches for summer 2018 community events

March 17, 2018

Completion of Round 1 Online Survey

February 22, 2018

Township launches engagement process

February 27, 2017

Council approves development permit for McLoughlin Point 

January 23, 2017 

McLoughlin Point Wastewater Treatment Plant open house on proposed community amenities

October 2016

The Township of Esquimalt and the Capital Regional District Core Area Wastewater Treatment Project Board begin discussions on community amenities associated with locating a wastewater treatment plant at McLoughlin Point in Esquimalt.